Azure Migration Assessment: 10-WK Implementation

Campana & Schott GmbH

We combine Azure assessment services with our consultancy approach to develop a ready-to-use migration plan. Migration Plan + Microsoft Azure Holistic Business Case.

Build the right Azure migration path based on comprehensive analytics and full transparency across your infrastructure. Weekly Agenda for a 10 Weeks Implementation Project :

· Week 1: Kick-off, Envisioning and Planning:
o Analysis of your company's on-premises infrastructure o Outcome: Baseline of desired results from Assessment phase · Week 2: Scope definition of quantitative assessment o Agreement on assessment scope o Outcome: Signature of Letter of Engagement
· Week 3: Launch of quantitative assessment - Server Level o Installation of assessment tool suite o Outcome: Assessment tool is installed to perform a first analysis
· Week 4: Launch of qualitative assessment – Application Level
o Definition of in-scope applications for a qualitative assessment of cloud migration / o Outcome: Overview of in scope applications and related contact persons in the client's organization · Week 5: Interview phase of application owners (Group I) o Interview of in-scope application owners o Outcome: Entry of interview results in outcome overview · Week 6: Interview phase of application owners (Group II) o Interview of in-scope application owners o Outcome: Entry of interview results in outcome overview · Week 7: Interview phase of application owners (Group III) o Interview of in-scope application owners o Outcome: Entry of interview results in outcome overview · Week 8: Synthesis of quantitative and qualitative assessment
o Summary of technical assessment results and synthesis with qualitative assessment results; Prioritization of 10 workloads to be migrated first o Outcome: Results presentation / Business Case · Week 9: Azure Migration Plan o Planning of resources, timeline and methods for migration o Outcome: Detailed migration plan for the first sprints and high-level timeline for future sprints · Week 10: Final presentation o Presentation of results and migration plan to stakeholders o Outcome: Joint agreement on next steps